Question1: which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?

Question2: When you create a sales order
When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?

Question3: Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

Question4: Your company manufactures materials whose specifications differ for each manufacturing process. Which application do you have to use in SAP S/4HANA to be able to track and use this information in all areas of logistics?

Question5: Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

Question6: You want to set up a make-to-order planning scenario for a finished material. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

Question7: Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?
Note: There are 2 correct answers to this question.

Question8: What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?

Question9: In documentation for MRP in Advanced Planning, you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Question10: Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Question11: Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?
Note: There are 2 correct answers to this question

Question12: Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.
what is the impact of this decision?
Note: there are 2 correct answers to this question

Question13: Which of the following elements does MRP take into account during net requirement calculation? Note:
There are 2 correct answers to this question.

Question14: What is the purpose of a reporting point confirmation in repetitive manufacturing?
Note: There are 2 Correct answers to this question?

Question15: Which business processes are affected by settings in the order-type-dependent parameters?
Note: There are 2 correct answers to this question.

Question16: How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,

Question17: If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

Question18: What does a line hierarchy in repetitive manufacturing represent?

Question19: How can you support a GMP (Good Manufacturing Practice)-compliant production process?
Note: There are 3 correct answers to this question.

Question20: What does the material type influence?
Note: There are 2 correct answers to this question.

Question21: You need to model goods receipt processing time in detailed scheduling. Which modeling options do you have?
Note: There are 3 correct answers to this question.

Question22: What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

Question23: You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?

Question24: which SAP application can be used for forecasting in Supply Chain Planning?
Note: there are 2 correct answers to this question.

Question25: Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

Question26: Which of the following questions do you have to answer before you start creating a bill of material (BOM)?

Question27: What can you use heuristics in Advanced Planning (PP/DS) for?

Question28: What is the work center hierarchy in capacity planning?

Question29: What data can you maintain in the subitems of a bill of material (BOM)?
Note: There are 2 correct answers to this question.

Question30: Which information is required when you create a product master in SAP S/4HANA?
Note: There are 2 correct answers to this question.

Question31: In the Capacity Scheduling Table, which settings can you select for the planning strategy?
Note: There are 3 correct answers to this question.

Question32: Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.

Question33: What does forecasting in the demand planning cycle include?
Note: There are 3 correct answers to this question

Question34: How can you set up a material as a phantom assembly?
Note: There are 2 correct answers to this question

Question35: Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA.
When can you use mode selection?

Question36: You want to schedule an operation finitely, without removing other operations. Which scheduling strategy do you select?

Question37: You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Question38: How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.

Question39: where does the system check master data selection settings during the creation of planned orders and production orders?
Note: There are 3 Correct answers to this question.