Question1: What does it mean for the production planner when MRP works with infinite capacities?

Question2: In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run?Note:
There are 2 correct answers to this question.

Question3: You are creating a production order manually. What activities are involved in this process?
There are 3 correct answers to this question.

Question4: Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? There are 3 correct answers to this question.

Question5: What are properties of MRP Live? There are 2 correct answers to this question.

Question6: You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?

Question7: What do you use to schedule operations from planned orders so that the production plan can be fulfilled?

Question8: What are some of the advantages of using Kanban? There are 2 correct answers to this question.

Question9: If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?

Question10: Your project team decides to use a make-to-order planning strategy for a strategic material in discretemanufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.

Question11: A planner updated a production order status from partially confirmed "PCNF"to technically completed "TECO" by mistake.
What impact would this have to other users for this specific production order?

Question12: Where can you find the latest in version of the Simplification List for SAP S/4HANA?
Please choose the correct answer.

Question13: Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? Note: There are 3 correct answers to this question.

Question14: Which time elements can be reduced by a reductionstrategy? Note: There are 3 correct answers to this question.

Question15: A material has been set up as a phantomassembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?

Question16: In which data objects do you maintain the production in as the work center for repetitive manufacturing?
There are 2 correct answers to this question.

Question17: For what production type are production orders used?

Question18: What are the possible categories for the Business Partner master data object in SAP S/4HANA?
There are 3 correct answers to this question.

Question19: A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?

Question20: For a production version to be valid and consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.

Question21: Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?

Question22: How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.

Question23: You need to model goods receipt processing time in Detailed Scheduling. Which modelling options do you have? Note: There are 2 correct answers to this question.

Question24: You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?

Question25: You want to represent setup time as a graphical object in the Detailed Scheduling Planning Board. Which actions are needed? There are 2 correct answers to this question.

Question26: Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? Note: There are
3 correct answers to this question.

Question27: What is the first step in the MRP run?

Question28: In the first step, you have created master recipes. In which sequence are the additional objects created?

Question29: During planning you are facing an overload situation on a resource. Which activities do you consider to create a feasible production plan? There are 3 correct answers to this question.

Question30: Duringproduction order creation, several valid production versions are found. How does the system choose the product conversion?

Question31: The pegging situation was changed because of an MRP heuristic run. What is a capability of dynamic pegging?

Question32: What are the possible results of a production planning run inAdvanced Planning (PP/OS)? Note: There are 3 correct answers to this question.

Question33: When a developer creates a new SAP Fiori app, they begin by selecting a template to ensure the application has a consistent look-and-feel. What types of templates can a developer choose? There are 3 correct answers to this question.

Question34: What is the difference between co-products and by-products?

Question35: In which customizing activity do you set up automatic routing selection production orders?
Please choose the correct answer.

Question36: What are the three layers in the SAP Best Practices Content for SAP S/4HANA? There are 3 correct answers to this question.

Question37: You have a quality control check to avoid using a high-value component tin faulty materials in subsequent assembly operations. How do you account for potential scrap of the high-value material?

Question38: Which data model changes have been implemented in Sales and Distribution? There are 3 correct answers to this question.

Question39: Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.

Question40: What are the key aspects of SAP S/4HANA? There are 2 correct answers to this question.

Question41: Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.

Question42: A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR? There are 2 correct answers to this question.

Question43: You are using the document management system (DMS) . Where should the DMS document links be assigned, to have them automatically copied to production orders?
There are 2 correct answers to this question.

Question44: You want to integrate an existing planned order into Advanced Production Planning. Which report do you use? Please choose the correct answer.

Question45: Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

Question46: What does the bill of material usage (BOM usage) control at the BOM item level? There are 2 correct answers to this question.

Question47: How would you define pegging in the context of Advanced Planning?

Question48: You produce your material based on a forecast derived from historical sales and expect it to be in inventory when your customer orders. If customers order more that the forecasted quantity, you want to increase production to try to meet the extra demand. Which is the appropriate planning strategy to use?

Question49: What are drawbacks of the separation of OLTP and OLAP? There are 4 correct answers to this question.

Question50: What does the industry sector determine? Note: There are 2 correct answers to this question.

Question51: You want to schedule an order in the graphical planning board. What are valid planning directions?
There are 2 correct answers to this question.