QuizUN
1. Question Content...
EXPLANATION
Answer: X - EXPLANATION Content.
Question1: The settings for MRP can be maintained at different levels. If settings have been maintained in differentplaces, in which sequence does the system search for the MRP settings?Please choose the correct answer.Response:
Question2: Which of the following are included as SAP S/4HANA Sales Simplifications?There are 3 correct answers to this question.Response:
Question3: The pegging situation was changed because of an MRP heuristic run. What is a capability of dynamicpegging?Response:
Question4: In order to use strategy 70 - Planning At Assembly Level, what order field must be set besides theplanning strategy?Please choose the correct answer.Response:
Question5: What Kanban status automatically posts goods receipt with reference to the procurement element?Please choose the correct answer.Response:
Question6: What does the bill of material usage (BOM usage) control at the BOM item level?There are 2 correct answers to this question.Response:
Question7: You want to procure your material components based on a forecast for the finished material derivedfrom historical sales. When customers order, you produce the finished product and reserve it for thatparticular order.Which is the appropriate planning strategy to use?Please choose the correct answer.Response:
Question8: What is SAP's strategic solution to perform Sales and Operations planning when you use SAP S/4HANAManufacturing?Please choose the correct answer.Response:
Question9: The procurement type of your material is set to "E" for In-house production. Which of the following isvalid to determine a source of supply in SAP S/4HANA?Please choose the correct answer.Response:
Question10: Your customer complains about incorrect duration for production order operations. What time elementscould cause the issue?There are 3 correct answers to this question.Response:
Question11: When do you recommend the use of repetitive manufacturing?There are 2 correct answers to this question.Response:
Question12: In Make-to-order production, which field controls whether the components will be planned as salesorder specific stock?Please choose the correct answer.Response:
Question13: The material master of your finished product contains MRP type "PD". You set a manual firming date inthe stock requirements list. Which of the following will firm planned orders"There are 2 correct answers to this question.Response:
Question14: Which task list types can have parallel sequences?There are 2 correct answers to this question.Response:
Question15: What is the correct sequence of the following Activate methodology phases?Please choose the correct answer.Response:
Question16: Where can you maintain consumption mode and consumption periods for planning strategies?There are 2 correct answers to this question.Response:
Question17: A planner updated a production order status from partially confirmed "PCNF" to technically completed"TECO" by mistake.What impact would this have to other users for this specific production order?Please choose the correct answer.Response:
Question18: A resource was created in SAP S/4HANA PP/DS through the internal CIF integration and named"W1904_1000_001". What does the suffix 001 in the resource name represent?Please choose the correct answer.Response:
Question19: In which of the following master data objects can you define the production order default storagelocation for a material component?There are 2 correct answers to this question.Response:
Question20: Which of these are layers in SAP Best Practice content?There are 3 correct answers to this question.Response:
Question21: Which times are used for Basic Date Scheduling of manufacturing planned orders in MRP?There are 2 correct answers to this question.Response:
Question22: Before a user can add multiple production versions in a material master, what information should becollected?There are 3 correct answers to this question.Response:
Question23: You are using heuristic SAP_ERP_001. Which of the following criteria are included in the automaticsource determination logic when a planned order is created?Please choose the correct answer.Response:
Question24: A customer is considering switching from order-related settlement to product-related settlement. Whatare capabilities of cost collectors?There are 2 correct answers to this question.Response:
Question25: What steps are possible in a PP/DS production planning run?There are 3 correct answers to this question.Response:
Question26: In which customizing activity do you set up automatic routing selection for production orders?Please choose the correct answer.Response:
Question27: Which of the following is an advantage of MRP Live and NOT available in classical MRP?There are 2 correct answers to this question.Response:
Question28: Which functional capabilities does the Detailed Scheduling Board have?There are 2 correct answers to this question.Response:
Question29: A planner wants to interactively resolve an overload situation on a resource using advanced planningtools without any automatic rescheduling activity by the system.Which combination of settings for resource and detailed scheduling strategy are required to receiverelated alerts?Response:
Question30: In which data object is the production line (Repetitive manufacturing relevant work center) maintained?Please choose the correct answer.Response:
Question31: On which of the following levels can you influence the availability check for the components ofproduction orders?There are 2 correct answers to this question.Response: